Campus-Wide Wi-Fi Service
Wi-Fi (wireless network) has become an important way to communicate, collaborate and learn on college campuses.
Vision 2020’s Facilities and Environment Working Group identified Wi-Fi as a required standard for information technology at NIU. ITS is working with the Office of the Provost and Housing to achieve 100 percent Wi-Fi coverage in all student and academic spaces.
See the Interactive Campus Web Map and choose Wireless Internet under Legend to see current wireless coverage.
Wi-Fi Implementation Schedule
| Deployment Target Date | Building | Existing Access Points (APs) | Vision 2020 APs | Additional APs Requested | Total APs | Deployment Status |
|---|---|---|---|---|---|---|
| Aug '12 | Campus Life |
2
|
7
|
0
|
9
|
100% Installed & On-Air |
| Aug '12 | Campus Rec. Center |
0
|
18
|
0
|
18
|
100% Installed & On-Air |
| Aug '12 | Evans Rec. Center |
0
|
6
|
0
|
6
|
100% Installed & On-Air |
| Aug '12 | Founders Library |
15
|
22
|
0
|
37
|
100% Installed & On-Air |
| Aug '12 | Holmes Student Center |
19
|
35
|
0
|
54
|
100% Installed & On-Air |
| Aug '12 | Douglas |
21
|
80
|
12
|
92
|
100% Installed & On-Air |
| Aug '12 | First Year Residence |
0
|
110
|
0
|
110
|
100% Installed & On-Air |
| Aug '12 | Northern View |
2
|
50
|
0
|
52
|
100% Installed & On-Air |
| Aug '12 | Stevenson |
22
|
102
|
14
|
116
|
100% Installed & On-Air |
| Oct '12 | Art |
5
|
9
|
0
|
14
|
100% Installed & On-Air |
| Oct '12 | Davis |
0
|
10
|
12
|
22
|
100% Installed & On-Air |
| Oct '12 | DuSable |
2
|
32
|
5
|
39
|
100% Installed & On-Air |
| Oct '12 | Faraday |
2
|
14
|
15
|
31
|
100% Installed & On-Air |
| Jan '13 | McMurry |
3
|
4
|
0
|
7
|
100% Installed & On-Air |
| Jan '13 | Music |
1
|
23
|
0
|
24
|
100% Installed & On-Air |
| Jan '13 | Psych-Math |
4
|
13
|
15
|
32
|
100% Installed & On-Air |
| Jan '13 | Smart Classrooms (SS 175, DD 30) | 0 | 2 | 0 | 2 | 100% Installed & On-Air |
| Aug '13 | Engineering |
4
|
17
|
0
|
21
|
100% Installed & On-Air |
| Aug '13 | LaTourette |
5
|
18
|
9
|
32
|
100% Installed & On-Air |
| Aug '13 | Montgomery |
7
|
8
|
12
|
27
|
100% Installed & On-Air |
| Aug '13 | Reavis |
2
|
7
|
6
|
15
|
100% Installed & On-Air |
| Aug '13 | Wirtz |
3
|
10
|
6
|
19
|
100% Installed & On-Air |
| Aug '13 | Gilbert |
0
|
40
|
0
|
40
|
100% Installed & On-Air |
| Aug '13 | Grant D |
0
|
31
|
0
|
31
|
100% Installed & On-Air |
| Aug '13 | Lincoln |
22
|
90
|
TBD
|
90
|
On Hold |
| Aug '13 | Neptune |
25
|
92
|
16
|
108
|
100% Installed & On-Air |
| Jan '14 | Stevens |
0
|
11
|
TBD
|
11
|
Part of Building Renovation |
| Jan '14 | Still Hall |
2
|
4
|
0
|
6
|
100% Installed & On-Air |
| Jan '14 | Still Gym |
0
|
6
|
0
|
6
|
100% Installed & On-Air |
| Jan '14 | Watson |
2
|
8
|
7
|
17
|
100% Installed & On-Air |